Sewage installations - Bypass ventilation
| Product | InstalSystem 5 |
| Type of article | FUNCTION AND TOOL |
| Source for translation | 2023-06-21 |
Description
The article describes methods of implementation of various cases of bypass ventilation in sewage installations.
Location in the program
The type of the stack is indicated in the Data table.

All necessary points should be specified.
Example of use
The program provides several schemes to perform such types of stacks. Schemes A-D are applicable to buildings from 3 to 5 floors (less or equal to 12m in height). Schema E - for the buildings with more than 5 floors (more than 12m in height)
- Schema A:
- Schema B:
- Schema С:
- Direct parallel ventilation: vent stack is connected to the sewage stack at the bottom near the stack foot and at the top to the vent cowl;
- Generate intermediate ventilation connections are made;
- Connection to the vent stack from each fixture on the first floor and from each sewage branch on the floors above.

4. Schema C.
- Schema D:
- Schema E:
- Direct parallel ventilation: vent stack is connected to the sewage collector. The connection must be made at least 2 m from the base of the stack;
- Generate intermediate ventilation connections should be made;
- Fixtures on the first floor are connected to the additional stack;
- The connection of the additional stack to the main stack is made by the means of a "vent loop".

6. Schema E.