Sewage installations - Bypass ventilation: Difference between revisions

From HelpSystem
Jump to navigation Jump to search
Line 29: Line 29:
The program provides several schemes to perform such types of stacks. Schemes A-D are applicable to buildings from 3 to 5 floors (less or equal to 12m in height). Schema E - for the buildings with more than 5 floors (more than 12m in height)
The program provides several schemes to perform such types of stacks. Schemes A-D are applicable to buildings from 3 to 5 floors (less or equal to 12m in height). Schema E - for the buildings with more than 5 floors (more than 12m in height)
* Schema A:
* Schema A:
** Direct parallel ventilation stack is connected to the sewage stack at the bottom near the stack foot and at the top to the vent cowl;
** Direct parallel ventilation: vent stack is connected to the sewage stack at the bottom near the stack foot and at the top to the vent cowl;
** ''<IS_TS id=LacznikiNaKazdejKondygnacji/>'' can be made or not depending on the project features.<br/>[[File:Bypass ventilation schema A.png|900 px|left|thumb|2. Schema A.]]<br clear="all"/>
** ''<IS_TS id=LacznikiNaKazdejKondygnacji/>'' can be made or not depending on the project features.<br/>[[File:Bypass ventilation schema A.png|900 px|left|thumb|2. Schema A.]]<br clear="all"/>
* Schema B:
* Schema B:
** Indirect parallel ventilation stack is connected to the branches on each floor;
** Indirect parallel ventilation: vent stack is connected to the branches on each floor;
** ''<IS_TS id=pinNameZaworOdpLubNapow/>'' is used like an ''<IS_TS id=EndOfSewerageLine/>'' for both stacks (''<IS_TS id=strKanalizacjaSanitarna/>'' and ''<IS_TS id=strKanalizacjaWentylacja/>'').<br/>[[File:Bypass ventilation schema B.png|900 px|left|thumb|3. Schema B.]]<br clear="all"/>
** ''<IS_TS id=pinNameZaworOdpLubNapow/>'' is used like an ''<IS_TS id=EndOfSewerageLine/>'' for both stacks (''<IS_TS id=strKanalizacjaSanitarna/>'' and ''<IS_TS id=strKanalizacjaWentylacja/>'').<br/>[[File:Bypass ventilation schema B.png|900 px|left|thumb|3. Schema B.]]<br clear="all"/>
* Schema С:
** Direct parallel ventilation: vent stack is connected to the sewage stack at the bottom near the stack foot and at the top to the vent cowl;
** ''<IS_TS id=LacznikiNaKazdejKondygnacji/>'' are be made on each floor;
** connection to the vent stack from each sanitary appliance on the first floor and from each sewage branch on the floors above.<br/>[[File:Bypass ventilation schema С.png|900 px|left|thumb|4. Schema C.]]<br clear="all"/>


==Additional informations==  
==Additional informations==  

Revision as of 08:35, 22 June 2023

Product InstalSystem 5
Type of article FUNCTION AND TOOL
Source for translation 2023-06-21


Description

The article describes methods of implementation of double stacks, which are a combination of sewage and ventilation bypass stacks.

Location in the program

The type of the stack is indicated in the Data table.

1. Pipe-run types.


All necessary points should be specified.

Example of use

The program provides several schemes to perform such types of stacks. Schemes A-D are applicable to buildings from 3 to 5 floors (less or equal to 12m in height). Schema E - for the buildings with more than 5 floors (more than 12m in height)

  • Schema A:
    • Direct parallel ventilation: vent stack is connected to the sewage stack at the bottom near the stack foot and at the top to the vent cowl;
    • Generate intermediate ventilation connections can be made or not depending on the project features.
      2. Schema A.

  • Schema B:
    • Indirect parallel ventilation: vent stack is connected to the branches on each floor;
    • Air admittance valve is used like an Element on top of stack for both stacks (Sanitary drainage and Ventilation conduit).
      3. Schema B.

  • Schema С:
    • Direct parallel ventilation: vent stack is connected to the sewage stack at the bottom near the stack foot and at the top to the vent cowl;
    • Generate intermediate ventilation connections are be made on each floor;
    • connection to the vent stack from each sanitary appliance on the first floor and from each sewage branch on the floors above.
      4. Schema C.

Additional informations

Optional section that contains additional information describing the function/element of the program..