Problem description

In the process of performing Thermal calculations of building, there may arise a necessity to take into account a false ceiling as a thermal Partition. The solution is detailed in this article.

Solution

  • Add additional storey level or Add internal storey level. For more information, see: Additional and internal storey levels;
  • Specify Hs (Storey elevation) in accordance with the Thickness of false ceiling indicated for the Main storey level;
  • Insert a Slab element on the created level;
  • Run Computation of building structure ;
  • Add and specify the Partition definition. For more information, see: Calculation of design heat load of rooms;
  • Make Thermal calculations of building.